Joy (chair) met with Mick Gilhooly of Segro for an update on progress.
SADC Environmental Compliance officers had visited earlier in the day and were satisfied with work hours and wheel washing.
British Pipeline Association are diverting the oil pipeline between Buncefield and Heathrow. The bypass is progressing with sections dug to formation, some have been capped and deep drainage is progressing along the route.
HCC Rural Estates have not come back to Segro regarding commercial woodland to the east of the site.
Part of the temporary Bund will be removed for access to remove the inherited Victorian and airfield detritus. The Bund work is likely to commence in June.
SADC consented hours are 6.30am – 8.30pm but in reality there is a 7am start and 7pm finish Saturday 7.30am to 1pm.
The London Colney roundabout will have a lane closure overnight on May 18th for improvements and new white lines.
Strabag will work with relevant bodies to ensure the Alan Williams turret on HCC land is restored. The cycle lane along the A414 is making good progress.
Strabag and Galldris will improve the underpass at Park St roundabout even though it is HCC’S responsibility. It will be cleaned up, repainted and lighting improved.
A team from Segro would like to hear your comments concerning the Country Park on Wednesday May 13th between 1.30pm and 6.30pm they will be around the Lakes/ Hyde Lane